Implementation Challenge
Optimizing the Existing Infrastructure
Limited installation space on the existing lighting towers and the requirement to retain part of the stadium's previous lighting system were among the key challenges of this project.
Golnoor's engineering team developed a hybrid lighting solution by redesigning the lighting layout and fixture positioning. In addition to the existing lighting towers, several Faraz LED stadium floodlights were installed on custom-engineered steel structures above the spectator stands. The design, fabrication, installation and commissioning of these structures were completed by Golnoor, enabling the project to achieve the required lighting performance for professional football.